Method of calculating cement ball mill capacity

Cement ball mill is commonly used crushing equipment in the industry ,the statistics on the output of the ball mill in actual production is an important basis for the report-type statistics of the production workshop. The data is mainly the statistics of the production of different shifts and the output of the ball mill, and we usually calculate the capacity of the mill. The basic methods are: the measuring method, the feeding weight measurement method, and the estimation of the output per ton of grinding body. Below, Dawning introduces you to the calculation of the specific yield of different methods.

1. Volume method
The bin method is one of the easiest methods for calculating the actual output of the ball mill. For the actual measurement, we take a simple weight measurement as an example, weigh a small iron drum of 1000 ml of water, and then we will Put the cement or raw material into it, tap it, smooth it, weigh it, then pour it out, fill it with water and weigh it again, then subtract the weight from the known weight to know the cement or raw The bulk density of the material, but this operation is only suitable for the production of a grinding bin, not for the production of more mills.

2.Feeding weight measurement
This kind of metering operation is limited by the various conditions of the ball mill production, and the obtained result can only be regarded as the approximate value of the ball mill production capacity. The specific application formula is
qR=feeding amount×C4
 qR is the amount of fine ore selected by the ball mill, the unit is t/h;
C4 is the content of the particles passing through the 0.08 mm square hole sieve in the material, and is measured in %.

3. Estimation of the output per ton of grinding body in the ball mill
The error of this method is relatively large and can only be used as a reference. According to the operating experience, the output of each medium-ton ball mill and raw material mill per ton of grinding body is 340-450 kg per hour, some In the case of 550 kg per hour, the cement ball mill can produce 300-400 kg per ton of grinding body per ton, and sometimes even 450 kg per hour.

However, as of now, there is no precise calculation method that can accurately calculate the specific output of the ball mill. You can decide which method to calculate the output based on the actual production situation.


Method of calculating cement ball mill capacity

评论

此博客中的热门博文

What if the plastic shredder is blocked

Plastic shredder is specially designed to tear up plastics, building templates, wooden pallets and other waste wood, long time to tear up the work, there may be some problems. For example, in the process of production, fast feed, plastic shredder suddenly appeared blocked, what to do? Plastic shredder, congestion is more common problems are basically caused by not timely maintenance, regular cleaning, accumulate over a long period, can jam during production, not only affect the production, can also harm the plastic shredder. This is the reason why the plastic shredder is blocked. Plastic shredder failure requires you to pay attention to in time, if it is found that the shredding machine production, and the same raw material, check the damper is in place and pipes with and without air leakage, etc., the shredding machine jams are common faults, the possibility is there are four: 1: may be the body design problem; 2: the raw material is put in too fast; 3: it is the pipe of the discharg...

Scrap metal shredder

Start up and operation steps of dual shaft shredder

The industrial shredder expert explains the steps of starting the dual shaft shredder: 1. The starting motor of the dual shaft shredder operates under no load. If the technical conditions of each part are normal, it can only operate under load after the rotating speed is normal. 2. During the operation of the dual shaft shredder, there shall be no magnetic jamming and friction sound. 3. The screen shall be installed firmly, sealed, without leakage, and the screen frame shall be fixed tightly. 4. In case of abnormal noise, blocked discharge, overheated bearing or motor during the operation of the dual shaft shredder, stop feeding, stop inspection and troubleshooting. 5. At the end of the work, the crusher and fan can be stopped only after the materials in the machine are completely removed. 6. Safety production must be strictly guaranteed during operation. Do not increase the speed of the dual shaft shredder at will. Check the cotter pin on the pin shaft frequently. If it is excessivel...